• Reconstruction of one of the largest substation located in Minsk region - «Minsk Severnaya330» - completed OJSC “AGAT – Control Systems» successfully supplied Automated energy control and metering system and carried out commissioning works

    18.09.2019
    Reconstruction of one of the largest substation located in Minsk region - «Minsk Severnaya330» - completed OJSC “AGAT – Control Systems» successfully supplied Automated energy control and metering system and carried out commissioning works
    Reconstruction of one of the largest substation located in Minsk region - «Minsk Severnaya330» - completed OJSC “AGAT – Control Systems» successfully supplied Automated energy control and metering system and carried out commissioning works

    The commissioning certificate has been signed after the reconstruction of one of the largest Capital’s substations 330/110/10 kW «Minsk Severnaya». It is an affiliated branch of «Minsk electric power networks» of the Republican Unitary Enterprise «Minskenergo».
    The modernization of «Minsk Severnaya» substation lasted 4 years. The decision on the comprehensive reconstruction of the substation was made along with the implementation of the milestone project in the Republic of Belarus. It is the «Construction of Nuclear Power Plant in the Republic of Belarus. Power generation and connection to electric power system». OJSC “AGAT – Control Systems” took active participation in the previously mentioned project.
    North China Power Engineering Co., Ltd. of China Power Engineering Consulting Group (NCPE) acted as General Contractor. The construction and assembly works were carried out by “Electrocentrmontazh” PLC under technical supervision of the Republican Unitary Enterprise “Minskenergo” and construction design supervision of the Republican Unitary Enterprise «Belenergosetprojekt». The supplies and commissioning works with respect to the Automated energy control and metering system of 1-4 start-up facilities of the first phase of the construction project were carried out by OJSC “AGAT – Control Systems”.
    Since the substation "Minsk Severnaya" provides power to a large number of consumers, the main feature of the reconstruction was that the works were carried out in a limited area without turning off the main equipment at the existing power facility. During the reconstruction, the power was supplied to the consumers continuously.
    The result of the reconstruction is high-tech Automated energy control and metering system based on the software of Automated Control System for the Technological Processes «AGAT-2000» applying the most advanced energy meters.