On 07.09.2018 The ceremony of the commissioning of the facility "Construction of cable lines 110 kV Thermal Power Plant-3 — Substation 110/10 kV «Podlesnaya» took place

On 07.09.2018 The ceremony of the commissioning of the facility "Construction of cable lines 110 kV Thermal Power Plant-3 — Substation 110/10 kV «Podlesnaya» took place

 The specialists of OJSC “AGAT – Control Systems» did the following scope of work at the Podlesnaya substation on creation of automated electric power fiscal metering system:
  • - Equipment delivery for automated electric power fiscal metering system;
  • - Installation supervision of the automated electric power fiscal metering system at the electric power substation;
  • - Commissioning works of the automated electric power fiscal metering system at the electric power substation and put into trial operation.